Construction Quality Assurance: Closing an Island Dump


Quality Assurance  A systematic program designed to provide verification that quality control functions have been adequately performed and to verify that the total installation conforms to the plans and specifications. Usually performed by the Owner or Third Party Firm.


Quality Control  Testing and inspection functions performed to verify that specific parameters conform to the plans and specifications. Usually performed by the manufacturer or the installer.


Quality Assurance Team  Owner  Design Engineer  Construction Manager  CQA Monitor  Contractor


CQA Program  Pre-construction  Construction  Post-construction


Pre-Construction CQA  Meetings  Conformance testing  Shipping


Meetings  Pre-bid  Pre-construction  Progress  Final walkthrough


Conformance Testing  Process of testing and analysis of materials prior to deployment to ensure that the physical properties of the material are in accordance with the specifications.


Types of Conformance Testing  Manufacturing plant  Manufacturer’s plant audit  Third party laboratory


Manufacturing Plant Quality Control  Raw material  Geomembrane rolls  Post-production handing and testing


Raw Material  Resin manufacturer’s documentation  Sampling from the rail car  Resin testing  Storage


Polyethylene Resin (white) Compounded Resin (black)


Rail Cars Unloading Resin


Resin Properties  Density  Melt index  Carbon black  Oxidative induction time


Carbon Black Dispersion Test


Carbon Black Dispersion Chart


Geomembrane Extrusion  Blown film  Flat die




Post-Production Handling and Testing  Thickness  Labeling  Storage  Laboratory conformance testing


Micrometer for Thickness Testing


Storage of Geomembrane Rolls


Geomembrane Labels  Roll number and date  Resin manufacturer  Roll width and length  Thickness  Blend number


Laboratory Testing and Labeling for Geomembrane Rolls


Laboratory Testing  Frequency  Retains  Testing


Physical Properties  Tensile  Specific gravity  Puncture  Carbon black


Start of Tensile Test


Completion of Tensile Test


Manufacturer’s Plant Audit  Third party audit  Evaluation of quality control procedures


Plant Audit for Ordot Dump Closure


Inspection of a Plant  Review of manufacturer’s quality control program  Delivery, storage, and handling of resin  Production of geomembrane  Storage and labeling of the geomembrane


Third Party Laboratory Testing  Delivery  Sampling  Testing


Indicator Parameters  Density  Tensile properties  Asperity height  Carbon black  Puncture


Delivery of Geomembrane to the Site  Manufacturer’s certification  Off-loading  Logging of rolls by CQA Monitor  Cross checking conformance testing rolls


Pre-Construction Complete  Manufacturer’s testing and documentation complete  Third party conformance testing complete  Quality assurance engineer’s review complete


Construction CQA  Subgrade preparation  Geomembrane deployment and field seaming  Nondestructive testing  Destructive testing  Repairs


Subgrade Preparation  Written acceptance from installer  Compaction  Particle size  Desiccation


Subgrade Preparation


Geomembrane Deployment  Subgrade preparation accepted  Approved panel layout  Panel and seam identification  Weather conditions


Geomembrane Deployment


Field Seaming  Trial weld  Fusion welding  Extrusion welding


Trial Welds  Every four hours  Three feet in length  Welding


Trial Weld Preparation


Trial Weld Testing


Fusion Welding  Heat and pressure  Single wedge  Double wedge


Fusion Welding


Double Wedge Welder


Extrusion Welding  Heat bond  Oxidation removal  Welding


Oxidation Removal


Extrusion Weld


Nondestructive Seam Testing  Vacuum box  Air pressure  Spark test


Vacuum Box


Air Pressure Testing


Destructive Seam Testing  Frequency/selection  Shear testing  Peel testing


Destructive Seam Sample


Destructive Coupon Cutting


Destructive Shear Test Using Tensiometer


Repairs  Seams  Sheet


Documentation  Daily records  Observation and test data sheets  Progress reports  Construction deficiency reports  Final certification reports


Ordot Dump Closure  Existing conditions  Final grading  Cover system


Ordot Dump Existing Conditions


Ordot Dump Final Grading


Ordot Dump Cover System  Lower geocomposite  LLDPE geomembrane  Upper geocomposite  Geocell  Landfill gas extraction system  Leachate collection system


Cover System Detail


Cover System Installation


Geocell Installation


Drilling of Landfill Gas Extraction Well


Installation of Landfill Gas Extraction Well


Landfill Gas Flare


Leachate Collection Trench Construction


Stormwater Collection With Concrete Filled Geocell


Stormwater Collection Structures


Site Specific CQA Issues for the Ordot Dump Closure  Weather  Leachate seeps  Remote location  Waste relocation  Stormwater control


Current Closure Construction Progress  Photographs


Severe Weather Conditions


Initial North Slope Conditions


Grading and Relocation of Waste on North Slope


Grading of Waste on North Slope


Placement and Compaction of Waste on the Top Deck


Placement of Foundation Layer Over Final Waste Grades


Compaction of Foundation Layer Over Final Waste Grades


Installation of Leachate Seep Drain


Excavation of Temporary Leachate Storage Pond


Final Grading of Temporary Leachate Storage Pond


Installation of Bottom Geomembrane in Temporary Leachate Storage Pond


Installation of Floating Cover in Temporary Leachate Storage Pond


Construction of Leachate Storage Tank Pad


Excavation and Relocation of Waste Outside of the Final Cover (WRA 2)


Placement and Compaction of Clean Soil in Waste Relocation Area 2


Waste Relocation Area 1 Waste Removal and Backfilling With Clean Soil


Removal of Waste in Waste Relocation Area 4


Overview of Waste Relocation Area 4


Identification of Miscellaneous Waste for Removal


Access Road Construction


Excavation of Water Diversion Trench


Abandonment of Existing Landfill Gas and Groundwater Monitoring Wells


Delivery of Geomembrane Rolls


Logging in Geomembrane Rolls


Questions?