Update on Waterloo Estate Regeneration presentation, 16 June 2022

Page 1

H AV E R I N G ESTATE REGENERATION

Welcome to the Update on Waterloo Estate Regeneration for Cotleigh Road Residents 16th June 2022


H AV E R I N G ESTATE REGENERATION REPRESENTATIVES Paul Walker – Assistant Director (LB Havering) Joe Arthur – Development Manager (Wates) Keith Ward – Project Director (Wates) Neil Shaftain – Project Manager (Wates) Paul Dwyer - Regeneration & Community Liaison Officer (LB Havering) Michael Rourke – Project Manager (LB Havering) Asha Saroy – Associate Director (GL Hearn)


H AV E R I N G ESTATE REGENERATION AGENDA 1.

Demolition Progress

2.

Next Steps

3.

Meanwhile Use Space

4.

Project Programme

5.

Contacts

6.

Questions


H AV E R I N G ESTATE REGENERATION

UPDATE ON DEMOLITION PROGRESS


H AV E R I N G ESTATE REGENERATION DEMOLITION PROGRESS •

Demolition is now complete and Erith have left site

The demolition material has now been removed from site

Capping layer to any remaining material is now complete

Full time security is still present on site along with camera monitoring


H AV E R I N G ESTATE REGENERATION

NEXT STEPS


H AV E R I N G ESTATE REGENERATION •

Works will commence to widening the bell mouth at the junction of London Road and St Andrews Road in late 2022, although this is reliant on statutory authorities.


H AV E R I N G ESTATE REGENERATION

MEANWHILE USE SPACE


H AV E R I N G ESTATE REGENERATION MEANWHILE USE SPACE •

Area of land between the Parish Centre and St Andrews Church identified as possible the first phase of meanwhile use space for the site

This part of the site is likely to be one of the later phases and therefore we would like to utilise this space for community benefit and social value


H AV E R I N G ESTATE REGENERATION


H AV E R I N G ESTATE REGENERATION

PROGRAMME


H AV E R I N G ESTATE REGENERATION PROJECT PROGRAMME - KEY MILESTONES Buildings 1&2 Works Commence

PHASE 1: Detailed design continues / London Rd bellmouth work / Meanwhile use space Jun 22

Jul 22

Aug 22

Sep 22

Oct 22

Nov 22

Dec 22

Jan 23

Feb 23

Mar 23

Apr 23

May 23

PHASE 2: Phasing plan developing / Site wide infrastructure work We are here

Jun 23

Jul 23

Aug 23 Sep 23 Oct 23 Nov 23

Dec 23 Onwards


H AV E R I N G ESTATE REGENERATION

KEY CONTACTS


H AV E R I N G ESTATE REGENERATION KEY CONTACTS: For any queries on the day to day activities on site (including anything urgent), please contact:

For all Waterloo related queries, please contact:

Neil Shaftain Project Manager Wates Residential Mobile: 07729 105 019 Email: Neil.Shaftain@wates.co.uk

Paul Dwyer Residents Liaison officer Paul.Dwyer@havering.gov.uk 01708 431154 Mobile: 07976 539160 Regeneration@havering.gov.uk

Keith Ward Project Director Wates Residential Mobile: 07516 131 341 Email: Keith.Ward@wates.co.uk


H AV E R I N G ESTATE REGENERATION

QUESTIONS?