NE CR 1474
NE CR 234 to US 301
4.3
$2,900,000
$2,635,542
Gas Tax Bond
Completed 2008
PROJECT DESCRIPTION • Full depth reclamation. • Construction of 4’ wide paved shoulders. • Drainage improvements including culvert replacement and extensions. This project was a full depth reclamation of NE CR 1474 from NE CR 234 to US 301 with the addition of 4 foot paved shoulders. This project was designed by Kimley-Horn and Assoc., Inc. and was constructed in-house. On February 11, 2008, the Alachua County Public Works Department began the full depth reclamation of CR 1474. The construction was expected to last 180 days. With associated change order days, the construction actually took 185 days. This was the in-house Construction Crew’s first major full depth reclamation. Funding for this project came from Gas Tax Bond revenues that had been approved by the Board in April 2005.
JUNE 24, 2010
ALACHUA COUNTY PAVEMENT MANAGEMENT PROGRAM UPDATE REPORT